The PTG website highlights 29 projects to be implemented by different agencies of the Philippine government. By tapping into the interactivity and speed of the internet, the website delivers the latest updates on projects. It also serves as a venue to develop discussions and get feedback from the public.

UPDATE: LRT Line 1 North Extension (MRT-LRT) Loop

2009 March 11
by ptgwebsite

(11 March 2009)  We have obtained pictures of the ongoing construction of the LRT Line 1 North Extension (MRT-LRT) Loop from Thirdy Gomez.

LRT Line 1 North Extension (MRT-LRT) Loop

LRT Line 1 North Extension (MRT-LRT) Loop

LRT Line 1 North Extension (MRT-LRT) Loop

LRT Line 1 North Extension (MRT-LRT) Loop

LRT Line 1 North Extension (MRT-LRT) Loop

LRT Line 1 North Extension (MRT-LRT) Loop

LRT Line 1 North Extension (MRT-LRT) Loop

Click here to read more about the LRT Line 1 North Extension (MRT-LRT) Loop project.

UPDATE: Government Hospital Upgrading (Nationwide)

2009 February 9

The Department of Health (DOH) has sent an update regarding the construction of Out Patient Department (OPD) Building Phase III in Region I Medical Center, Dagupan City. This is part of the Government Hospital Upgrading (Nationwide) project.

As of 20 January 2009, 43% of the project has been accomplished. In detail:

Clearing/Removal of Existing Structures and Obstructions: 80%

Excavation: 100%

Backfiling: 58%

Forms and scaffolding: 90%

Reinforcing steel bars: 85%

Concrete works: 71%

Masonry works: 28%

Plastering works: 0%

Ceiling works: 0%

Roffing works: 0%

Plumbing works: 10%

Drainage system and Catch Basin: 0%

Electrical Works: 10%

Painting works: 0%

Railing and fire exit: 0%

Doors and windows: 0%

UPDATE: Government Hospital Upgrading (Nationwide)

2009 January 28

The Department of Health (DOH) has sent an update regarding the construction of Out Patient Department (OPD) Building Phase III in Region I Medical Center, Dagupan City. This is part of the Government Hospital Upgrading (Nationwide) project.

As of 5 January 2009, 35% of the project has been accomplished. In detail:

Clearing/removal of existing structures and obstructions: 80%

Excavation: 100%

Backfiling: 45%

Forms and scaffolding: 80%

Reinforcing steel bars: 70%

Concrete works: 45%

Masonry works: 22%

Plastering works: 0%

Ceiling works: 0%

Roofing works: 0%

Plumbing works: 10%

Drainage system and Catch basin: 0%

Electrical works: 10%

Painting works: 0%

Railing and fire exit: 0%

Doors and windows: 0%

PHP24M is the approved budget for the project. The financing source stated is the general fund.

Project ref. # 08-022

SARO No. BMB-B-08-0003318

UPDATE: Northrail Project (Phases 1 and 2)

2009 January 21

15 January 2009: A news article published in the Philippine Daily Inquirer on January 15, 2009 reported that a civil engineer has questioned the capability of CNMEC, the Chinese construction which was awarded the USD550M Northrail project. Rene Santiago was the civil engineer who was called in as the expert witness in the UP Law Center’s review of the Northrail contract. Engr. Santiago has cited the following parts of the contract that he found “strange”:

  • CNMEC did not have any known experience in constructing a railway system,much less any railway project similar to the Northrail project. This was verified after checking CNMEC’s company website.
  • The condition that “Chinese standards” must be used in the construction of the railway system. Philippine standards should be observed in infrastructure projects built in the country.
  • The project was to be insured by a Chinese firm. Infrastructure projects in the country are to be insured by the GSIS.

UPDATE: Northrail Project (Phases 1 and 2)

2008 December 3

3 December 2008 According to the Pro-Performance System (PPS) report as of October 31, 2008:

ROWA for additional right-of-way is ongoing. Negotiation with CNMEG is ongoing regarding the technical and commercial aspects of the project.

Click here to read more about the Northrail Project (Phases 1 and 2).

UPDATE: Mainline South Railway (Phases 1a)

2008 December 3

3 December 2008 According to the Pro-Performance System (PPS) report as of October 31, 2008:

Bidding for the rehabilitation/reinforcement/reconstruction and replacement of weak bridges is ongoing.

Click here to read more about the Mainline South Railway (Phase 1a) Project.

UPDATE: Mainline South Railway (Phases 1b and 2)

2008 December 3

3 December 2008 According to the Pro-Performance System (PPS) report as of October 31, 2008:

For updating of FS.

Click here to read more about the Mainline South Railway (Phases 1b and 2) Project.

UPDATE: LRT Line 1 South Extension (Phases 1 and 2)

2008 December 3
by ptgwebsite

3 December 2008 According to the Pro-Performance System (PPS) report as of October 31, 2008:

The LRTA Board has favorably endorsed to NEDA the adoption of Official Development Assistance (ODA) as the financial scheme for the implementation of the project. Acquisition of properties affected by the project is ongoing.

Click here to read more about the LRT Line 1 South Extension (Phases 1 and 2) Project.

UPDATE: LRT Line 2 (Phase 2)

2008 December 3
by ptgwebsite

LRTA Website)

LRT Line 2 (Image source: LRTA Website)

(3 December 2008) According to the Pro-Performance System (PPS) report as of October 31, 2008:

Updating of FS is ongoing.

Click here to read more about the LRT Line 2 (Phase 2) Project.

UPDATE: MRT 3 Capacity Expansion

2008 December 3

(3 December 2008) According to the Pro-Performance System (PPS) report as of October 31, 2008:

For NEDA-ICC deliberation on the proposed funding source for the procurement of 48 brand new LRV units.

Click here to read more about the MRT 3 Capacity Expansion Project.