UPDATE: Government Hospital Upgrading (Nationwide)

2009 April 16

14 April 2009: The Department of Health (DOH) has sent an update regarding the construction of Out Patient Department (OPD) Building Phase III in Region I Medical Center, Dagupan City. This is part of the Government Hospital Upgrading (Nationwide) project.

As of 20 March 2009, 84.56% of the project has been accomplished. In detail:

Clearing/Removal of Existing Structures and Obstructions: 95%

Excavation: 100%

Backfiling: 98%

Forms and scaffolding: 100%

Reinforcing steel bars: 100%

Concrete works: 99%

Masonry works: 90%

Plastering works: 68%

Ceiling works: 0%

Roffing works: 87%

Plumbing works: 75%

Drainage system and Catch Basin: 0%

Electrical Works: 85%

Painting works: 0%

Railing and fire exit: 65%

Doors and windows: 60%